Installation
a) Despatch department will ensure that the packed items will be
delivered to the site with proper transport and handling and stored
at appropriate places.
b) Installation will be done according to the specifications and
approved shop drawings by using advanced tools.
c) Installation will be done according to the submitted installation
programme which is based on the main contractor’s programme.
d) Any damaged items at site will be returned to the factory for
rectification / replacement.
e) The site engineer/foreman will also liase with the main contractor
to coordinate with other trades working in the same area and will
ensure protection of our finished works until handing over with
cardboard or plastic sheets as appropriate. All installation and
fixing will be in accordance with the engineers requirements and
carried out with skilled workers.
f) The site engineer will submit request form for inspection and
approval of completed installation.
g) All rubbish (i.e. Packing and protection material) of Ajman Korea
will be removed to designated skip locations provided by main contractor.
h) Any snagging given will be attended on top priority basis.
i) Prior to handing over, our own inspection team will thoroughly
check our product and attend to the snags if any.
|
|